GR L 4195; (February, 1908) (Digest)
G.R. No. L-4195
THE ATLANTIC, GULF AND PACIFIC COMPANY, plaintiff-appellant,
vs.
THE GOVERNMENT OF THE PHILIPPINE ISLANDS, defendant-appellee.
February 18, 1908
—
FACTS:
On July 24, 1905, The Atlantic, Gulf and Pacific Company (plaintiff) entered into a contract with the Government of the Philippine Islands (defendant) to construct the Luneta Extension in Manila, which included a rock and timber bulkhead, dredging and filling, and foundations.
The contract specifications provided:
Article 5: The contractor is responsible for damages to the bulkhead and revetment from wave action or pressure of the revetment against the timber structure. However, if a break is caused by pressure resulting from the mud filling, repairs will be paid for by the Government.
Article 12: Losses of dredged materials, except those due to bulkhead failure from mud fill pressure (as per Article 5), will be deducted from final payment.
On May 1, 1906, a section of the bulkhead (200 feet long) was displaced by pressure from the inside mud fill, causing an opening through which a large quantity of fill escaped. This initial break, per the contract, made the Government liable for repairs.
While repairs for the May 1 break were underway and before they could be completed, a severe typhoon struck Manila Bay on May 18, 1906. The already damaged bulkhead, lacking support from the escaped inside fill, was extensively damaged and destroyed for about 1,800 feet by external pressure from the rock revetment, wind, and waves. A large additional quantity of fill escaped.
The plaintiff alleged that if the May 1 break (caused by inside pressure) had not occurred, the typhoon would not have caused any damage, as the structure would have been strong enough.
On May 24, 1906, after the typhoon damage was apparent, a supplementary contract was executed. This contract specifically acknowledged the May 1 break caused by inside pressure and provided for the Government to pay for its repairs. Critically, it specified quantities of materials (stone, clay, timber) for these repairs that corresponded to the May 1 break, not the much larger damage caused by the typhoon.
Subsequently, the plaintiff sought to recover damages for the typhoon, arguing it was a consequence of the initial break. The Government engineer, in a communication dated May 26, 1906, resisted this claim, stating that the contractor was responsible for “most of typhoon damage,” reserving the issue for future adjudication.
The Court of First Instance sustained the defendant’s demurrer, effectively dismissing the plaintiff’s claim for typhoon damages. The plaintiff appealed.
—
ISSUE:
Is the Government liable for the damages caused to the Luneta improvement by the typhoon of May 18, 1906, or is the contractor responsible for such damages, considering the prior break on May 1, 1906, which was caused by internal pressure and for which the Government admitted liability for repairs?
—
RULING:
The Supreme Court affirmed the judgment of the Court of First Instance, holding that the plaintiff (contractor) is responsible for the damage caused by the typhoon and cannot recover from the Government.
The Court’s reasoning is based on the interpretation of the contract, particularly the acts of the parties:
1. Contractual Stipulation: Specifications 5 and 12 explicitly state that the contractor is responsible for “all damages to the bulkhead and the revetment arising from wave action or from pressure of the revetment against the timber structure.” The typhoon damage was immediately occasioned by wave action and outside pressure, which the contract assigns to the contractor’s responsibility. The contract thus makes external pressure an “independent cause” for which the contractor assumes liability, even if an internal break preceded it.
2. Narrow Scope of Government Liability: The Government’s liability under Article 5 is specifically limited to “repairs to the structure” resulting from “pressure from within,” not from the lack of such pressure or from external forces.
3. Acts of the Parties (Supplementary Contract): The supplementary contract of May 24, 1906, is crucial. It was signed after the typhoon damage was apparent. Yet, it only provided for the repair of the May 1 break, specifying quantities for materials that clearly corresponded to the initial, smaller break and not the extensive typhoon damage. This act demonstrates that the parties, at that time, did not interpret their contract as imposing liability for the typhoon damage on the Government. If they had, they would have included the greater amounts required for the typhoon repairs or at least reserved the question.
4. Government’s Resistance to Claim: The communication from the Government engineer on May 26, 1906, immediately resisting the claim for typhoon damage, further supports the interpretation that the Government did not consider itself liable for such.
Therefore, interpreting the contract in light of the parties’ actions, particularly the supplementary agreement, the Court concluded that the contractor made itself responsible for the damage by the typhoon.
