GR 29298; (December, 1928) (Digest)
G.R. No. 29298 , December 15, 1928
REYNALDO LABAYEN, ET AL., plaintiffs. REYNALDO LABAYEN, appellant, vs. TALISAY-SILAY MILLING CO., INC., defendant-appellee.
DOCTRINE:
A party to a contract is relieved from the obligation to perform an act if its fulfillment becomes legally or physically impossible. Mere inconvenience, unexpected impediments, or increased expenses do not constitute impossibility. Furthermore, a contract is deemed subject to an implied condition that performance is not rendered impossible by physical conditions or the failure to secure necessary rights-of-way as stipulated.
FACTS
Reynaldo Labayen, owner of Hacienda Dos Hermanos, entered into a contract with Talisay-Silay Milling Co., Inc. (“La Central”) on August 27, 1919. The contract obligated the central to construct and operate a railroad to transport sugar cane from the planters’ haciendas, with a clause specifying it would build a line reaching a point “not farther than one mile from any of the boundaries of said plantation, whenever the contour of the land, the curves, and elevations permit the same.” Another clause (Mutual Obligations, par. 10) provided that in case of inability to secure necessary rights-of-way under reasonable conditions, the central could notify the planters’ committee and the contract’s effects would be suspended without liability.
The central built its railroad only up to the adjacent Hacienda Esmeralda No. 2, stopping about four kilometers short of Hacienda Dos Hermanos. Expert testimony established that extending the line to Labayen’s hacienda, while physically possible, would require a dangerous grade (4.84% to 7%), 26 curves, and cost approximately P80,000. Additionally, the right-of-way for the extension had to pass through lands owned by Esteban de la Rama, who refused to grant permission until 1924.
Labayen sued for damages amounting to P28,620 for breach of contract due to the central’s failure to extend the railroad and mill his cane in the 1920-1921 season. The central filed a cross-complaint for a debt of P12,114 owed by Labayen.
ISSUE
Was Talisay-Silay Milling Co., Inc. liable for breach of contract for its failure to extend the railroad to Hacienda Dos Hermanos and mill the plaintiff’s sugar cane?
RULING
NO. The Supreme Court affirmed the trial court’s judgment absolving the central from the complaint and condemning Labayen to pay on the cross-complaint.
1. On Physical Impossibility/Danger: The central’s obligation to build the railroad was expressly conditioned by the phrase “whenever the contour of the land, the curves, and elevations permit the same.” The evidence showed that while construction was technically possible, it would be “very dangerous.” The Court held that one cannot be obligated to perform an act that, when accomplished, would be dangerous to life and property. This constituted a physical impossibility within the meaning of Article 1184 of the Civil Code, which relieves a debtor from an obligation if its fulfillment becomes legally or physically impossible. The contract was subject to an implied condition that performance would not be impeded by such physical impossibility.
2. On Legal Impossibility (Right-of-Way): Independently, the central’s performance was also rendered legally impossible by its inability to secure the necessary right-of-way from Esteban de la Rama during the relevant period (1920-1921). This situation was precisely covered by paragraph 10 of the Mutual Obligations in the contract, which provided for suspension of the contract without liability in case of inability to secure rights-of-way under reasonable conditions.
3. General Principles Applied: The Court cited the universal contract law principle that a party must perform what they have agreed to do unless performance is rendered impossible by an act of God, the law, or the other party. Mere inconvenience, unexpected impediments, or increased expenses are not sufficient grounds for non-performance. However, in this case, the central successfully proved both physical danger and a legal impediment (lack of right-of-way), which constituted valid excuses for non-performance.
Consequently, the central was not liable for breach. Since Labayen’s defense against the cross-complaint was based on the same invalid theory of breach, he was rightly ordered to pay his debt to the central.
This is AI Generated. Powered by Armztrong.
