GR 165889; (September, 2005) (Digest)
G.R. No. 165889 September 20, 2005
SACOBIA HILLS DEVELOPMENT CORPORATION and JAIME C. KOA, Petitioners, vs. ALLAN U. TY, Respondent.
FACTS
Respondent Allan U. Ty paid a reservation fee to petitioner Sacobia Hills Development Corporation for a share in the True North Golf and Country Club. Sacobia approved his application subject to terms, including full payment of the purchase price and a condition that failure to settle obligations would result in forfeiture of 50% of amounts paid. Sacobia made representations about project timelines, including that the golf course would be playable by October 1999 and that necessary government permits would be secured. However, the Environmental Clearance Certificate was issued later than indicated.
Ty sought to rescind the contract and demanded a refund of his payments, citing Sacobia’s failure to complete the project as represented. He subsequently stopped payment on post-dated checks covering his balance. An ocular inspection by the trial court in 2002 found the golf course operational and playable, with only the clubhouse undergoing finishing touches. Sacobia maintained a no-refund policy and offered to assist Ty in reselling his share.
ISSUE
Whether respondent Ty is entitled to rescind the contract and obtain a refund of his payments due to alleged misrepresentations by Sacobia regarding project completion.
RULING
The Supreme Court ruled in favor of the petitioners, reversing the Court of Appeals. The legal logic centers on the nature of the parties’ agreement and the absence of a causal breach. The contract between the parties was primarily a contract of sale of a club share, not a construction contract with a strict completion period. The representations made by Sacobia regarding timelines were merely collateral inducements and did not constitute a principal obligation, the breach of which would warrant rescission under Article 1191 of the Civil Code.
The Court emphasized that the right to rescind a reciprocal obligation arises only upon a substantial breach of a principal condition. Here, the core obligation of Sacobia was to transfer the share upon full payment, which it was ready to do. The delay in the ancillary project development, influenced by external factors like permit issuance and weather, did not go to the essence of the sale. Furthermore, the ocular inspection confirmed the project’s substantial operability. Ty’s own failure to complete his payments constituted a breach of his principal obligation. Consequently, the terms of the notice of approval, providing for forfeiture of 50% of payments upon default, were upheld. Ty was ordered to pay the outstanding balance or be subject to the stipulated forfeiture.
