GR 144792; (January, 2006) (Digest)
G.R. No. 144792 ; January 31, 2006
GAMMON PHILIPPINES, INC., Petitioner, vs. METRO RAIL TRANSIT DEVELOPMENT CORPORATION, Respondent.
FACTS
Metro Rail Transit Development Corporation (MRTDC) awarded Gammon Philippines, Inc. the contract for constructing a podium superstructure for the MRT 3 project. A Notice of Award (NOA) and Notice to Proceed (NTP) were issued on August 27, 1997. MRTDC subsequently suspended the project due to a currency crisis, downsized it, and issued a new NOA/NTP on April 2, 1998, which it later rescinded. MRTDC then offered revised terms via a NOA/NTP dated June 10, 1998, which Gammon did not fully accept, leading MRTDC to award the contract to another company. Gammon sought reimbursement for costs incurred, but the parties failed to agree on the amount. Gammon thus filed a claim with the Construction Industry Arbitration Commission (CIAC), invoking an arbitration clause in the General Conditions of Contract referenced in the NOA. MRTDC challenged CIAC’s jurisdiction, arguing no signed contract containing an arbitration agreement existed.
ISSUE
Whether the CIAC validly acquired jurisdiction over the dispute despite the absence of a formally signed contract between the parties.
RULING
Yes, the CIAC has jurisdiction. The Supreme Court ruled that a formal signed contract is not a prerequisite for CIAC jurisdiction if there is a clear agreement to arbitrate. The legal logic is anchored on the intent of Executive Order No. 1008 to provide expeditious settlement of construction disputes. The Court found that the arbitration clause in the General Conditions of Contract, which was expressly incorporated by reference into the NOA/NTP documents, constituted a binding arbitration agreement. The series of NOAs and NTPs, along with the parties’ conduct (including Gammon’s preparatory work and MRTDC’s communications), established a meeting of minds on the essential terms of their construction agreement. The dispute—arising from the aborted contract and involving claims for reimbursement—is directly connected to that agreement and thus falls within the CIAC’s original and exclusive jurisdiction. The Court emphasized that the CIAC’s jurisdiction is determined by the existence of an arbitration clause in a construction contract or related documents, not by the mere physical signing of a single instrument.
