GR L 2886; (October, 1906) (Digest)
Digest: G.R. No. L-2886 (Valentin Reyes v. Juana Tanchiato, et al.)
FACTS:
1. On October 9, 1902, Valentin Reyes (plaintiff-appellee) and Juana Tanchiato (defendant-appellant) entered into a contract wherein the defendants sold to the plaintiff the bamboo (“cañas que contienen las matas o ponos”) on a specified tract of land.
2. The purchase price was 500 pesos, with 300 pesos paid upfront and the remaining 200 pesos payable by February 1, 1903.
3. The contract stipulated that the plaintiff could cut the bamboo from February 1, 1903, until April 30, 1903.
4. Reyes delayed payment of the final installment until April 7, 1903, and began cutting the bamboo in late April or early May, continuing until August 8, 1903, when the defendants stopped him.
5. Reyes claimed he had only cut half of the bamboo when prevented and sued for damages due to the defendants’ interference.
ISSUE:
Did the plaintiff violate the terms of the contract by failing to complete the cutting of bamboo by the agreed deadline (April 30, 1903), thereby forfeiting his right to damages?
RULING:
YES. The Supreme Court reversed the lower court’s decision, ruling in favor of the defendants.
1. Contractual Deadline: The contract explicitly stated that the cutting must be completed between February 1 and April 30, 1903. Reyes failed to comply, as he continued cutting until August.
2. No Valid Extension: Reyes claimed a verbal extension until June or July, but this was denied by the defendants and not binding. Even if true, the defendants allowed cutting until August, which did not legally extend the original deadline.
3. Breach of Contract: Since Reyes did not finish cutting by April 30, he violated the contract and thus had no right to damages for being stopped later.
Disposition: The case was remanded to the lower court with instructions to enter judgment for the defendants. No costs awarded.
Concurring Justices: Arellano, C.J., Torres, Mapa, Johnson, Carson, and Tracey.
