SECOND DIVISION
[ G.R. No. 218378, June 14, 2021 ]
NATIONAL POWER CORPORATION, PETITIONER, VS. BENGUET ELECTRIC COOPERATIVE, INC., RESPONDENT.
R E S O L U T I O N
LOPEZ, M., J.:
The principle of unjust enrichment under Article 22 of the Civil Code is not a catch-all provision that can be conveniently invoked when a party has suffered a loss. This is especially true when a contract exists between the parties.
This Petition for Review onย Certiorari1ย under Rule 45 of the Rules of Court assails the Decision2ย dated August 29, 2014 and Resolution3ย dated May 22, 2015 of the Court of Appeals (CA) in CA-G.R. CV No. 96352, affirming the Decision4ย dated September 15, 2010 and Resolution5ย dated November 10, 2010 of the Regional Trial Court of La Trinidad, Benguet, Branch 63 (RTC) in Civil Case No. 04-CV-2055 which declared the underBilling of National Power Corporation (NPC) against Benguet Electric Cooperative, Inc. (BENECO) for the period covering May 2000 to February 2004, as illegal, unjust, and unenforceable.
ANTECEDENTS
NPC is a government-owned and controlled corporation that supplies power to BENECO under a franchise agreement. In turn, BENECO distributes power to all its members and consumers in Baguio City and Benguet Province.6
On January 1, 1998, NPC and BENECO entered into a Contract of Sale of Electricity.7ย Subsequently, the parties executed a Transition Contract for the Supply of Electricity (Transition Contract) whereby NPC will supply electric power and energy to BENECO at multiple points of delivery, including the Irisan Substation.8ย In 1999, the NPC’s Metering Services Group installed the metering system in Irisan Substation and conducted several tests to determine the multiplier. After the tests, the NPC set the Current Transformer Ratio (CTR) at 75/5, which fixed the multiplier at 5,196.31.9ย The Irisan Substation was energized in March 2000.10
From May 2000 to February 2004, the NPC maintained the CTR at 75/5 and billed BENECO using 5,196.31 as the multiplier.11ย NPC granted BENECO a Prompt Payment Discount (PPD) every month as long as BENECO’s account was fully paid and updated.12
In February 2004, BENECO’s employee, Engineer Lawrence Umaming (Umaming), studied BENECO’s operations and discovered its low systems losses. Because of this, Engineer Umaming called the attention of the National Transmission Corporation (TRANSCO), the company which took over NPC’s transmission functions in 2004. TRANSCO conducted tests on BENECO’s billing meter and noticed that the CTR was set at 75/5 instead of 150/5, which means that NPC had been billing BENECO at half the correct amount of electricity delivered to it.13
Consequently, in a demand letter14ย dated May 13, 2004, NPC informed BENECO of its underbilling from May 2000 to February 2004, amounting to PI57,743,314.43 and requested BENECO to pay the amount. BENECO refused to pay the underbilling and argued that it resulted from NPC’s failure to discover the error in the metering device. In consequence, NPC revoked BENECO’s PPD privilege on June 23, 2004.15ย NPC also billed BENECO an additional amount of P7,870,456.14, representing the PPD and the interest charges from April 2004 to July 2004. Too, NPC notified16ย BENECO that it will issue a disconnection order if it does not pay the balance.17ย For these reasons, BENECO filed a Complaint18ย for injunction, damages, and other relief on September 30, 2004, before the RTC.19
BENECO inveighed that it is not liable for the underbilling amounting to P157,743,314.43. Under Section 25 of the Transition Contract, NPC is deemed to have waived its claims on any billing not corrected within ninety (90) days from BENECO’s receipt of the erroneous billing. Thus, BENECO is still entitled to a 3% PPD. Also, NPC’s failure to discover its own mistake for almost four years constitutes gross inexcusable negligence.20
For its part, NPC asserted that the use of an “inapplicable CTR” in BENECO’s metering device is not covered by Section 25. The use of the 75/5 CTR will not result in a wrong reading since the CTR only scales down the actual current flowing in the substation. Neither can it be considered as an arithmetical mistake or omission, or error due to an inaccurate meter. NPC even faulted BENECO for calling its attention only after the lapse of (4) years.21
During the trial, it was established that: (1) the determination of the billing multiplier is the sole responsibility of the NPC; (2) the NPC conducted several tests on the billing meter system to determine the correct multiplier before the substation was finally energized in 2000; (3) after conducting meter tests, NPC prepared Billing Meter Test Reports indicating the multiplier; (4) NPC undertook monthly readings of the meter for purposes of monthly billing; (5) BENECO has no access to the billing meter system of NPC; (6) NPC consistently indicated the multiplier of 5,196.31 in their Meter Reading Reports and monthly bills; and (7) NPC bills BENECO every month.22
On September 15, 2010, the RTC rendered a Decision23ย in favor of BENECO. Applyingย Panay Electric Co., Inc. v. Court of Appeals (Panay Electric)24ย andย Ridjo Tape & Chemical Corp. v. Court of Appeals (Ridjo Tape),25ย the RTC held that BENECO cannot be faulted for the wrong multiplier. NPC’s failure to determine the error is a case of negligence, and as such, it must bear the consequential losses.26ย Concerning BENECO’s entitlement to a PPD, the RTC agreed with BENECO that the underbilling is separate from the current monthly billings. Since BENECO has been paying its current monthly bills promptly, it is entitled to a PPD.27ย The decretal portion of the Decision reads:
WHEREFORE, judgment is hereby rendered in this case in favor of the plaintiff and against the defendants as follows:
1. Declaring the underbilling and related billings of NPC to Beneco as illegal, unjust, and unenforceable against the Beneco;
2. Enjoining permanently the defendants and all persons acting on their behalf or their orders from disconnecting Beneco’s electric supply, and enjoining defendants to reinstate the 3% Prompt Payment Discount on Beneco’s monthly bills from April 2004 and onward;
3. Ordering defendant NPC to pay Beneco attorney’s fees of P1,000.000.00;
4. Dismissing all other claims and counterclaims for lack of merit.
5. Cost against defendant NPC.
SO ORDERED.28
NPC moved for reconsideration, but the RTC denied the motion in a November 10, 2010 Resolution.29
Dissatisfied by the RTC’s ruling, NPC filed an appeal with the CA and raised the issue of whether the NPC can compel BENECO to pay the underbilling.30ย Acting on the appeal, the CA upheld the RTC’s finding that NPC’s gross negligence was the proximate cause of the underbilling. NPC could have easily determined the need to change the CTR setting with all its technologically advanced resources. On the other hand, BENECO has no way of determining the wrong CTR setting in the Irisan Substation based on its unusually low systems losses. Remarkably, BENECO’s systems losses, as shown on its Monthly Financial Statistical Report, pertain to its entire operation, not only the Irisan Substation. More so, BENECO had no participation in installing NAPOCOR’s metering system, determining the billing multiplier, and conducting billing meter tests. The RTC found no preponderant evidence showing that BENECO was equally at fault and ruled that NPC was solely responsible for the underbilling. Thus, NPC should bear the loss.31ย The CA dismissed NPC’s appeal and ruled as follows:
WHEREFORE, premises considered, the instant Appeal isย DENIED. The assailed Decision dated 15 September 2010 and Resolution dated 10 November 2010 issued by Branch 63, Regional Trial Court of La Trinidad, Benguet are herebyย AFFIRMEDย except the award of attorney’s fees in the amount of one million (P1,000,000.00) pesos which is herebyย DELETEDย for lack of factual and legal basis.
SO ORDERED.32ย (Emphases in the original.)
NPC filed a motion for reconsideration. However, the CA denied the motion in a Resolution33ย dated May 22, 2015.
Hence, this recourse.
NPC insists that BENECO is liable for the underbilling because it consumed the electricity from NPC but only paid half of the actual price. Otherwise, BENECO will be unjustly enriched.34ย Further,ย Panay Electric,35ย Ridjo Tape,36ย andย Manila Electric Company (MERALCO) v. Spouses Chua (Meralco)37ย cannot justify BENECO’s non-payment of the underbilling since BENECO is not similarly situated as the end-users in these cases. BENECO has the technical expertise to determine the use of a defective CTR in the Irisan Substation.38ย Lastly, NPC has the right to revoke the PPD because it is a mere privilege. BENECO was rightfully disqualified from enjoying the PPD privilege given its unpaid underbilling.39
ISSUES
NPC raised the issues of whether: (a) BENECO’s non-payment of the underbilling constitutes unjust enrichment; (b)ย Panay Electric,40ย Ridjo Tape,41ย andย Meralco42ย are applicable in the case at bar; and (c) BENECO is entitled to a 3% PPD.
RULING
The petition is partly meritorious.
BENECO’s liability for the underbilling
is based on contract, not the principle of
unjust enrichment.
At the onset, the CA correctly ruled that BENECO had no participation in NPC’s use of the wrong CTR setting, and therefore, NPC’s loss is the result of its negligence. Nevertheless, BENECO is liable for the underbilling representing the power bills corrected within the 90-day period based on Section 25 of the Transition Contract, not the principle of unjust enrichment.
Unjust enrichment exists when a person unfairly retains a benefit, money, or property against the fundamental principles of justice, equity, and good conscience.43ย The principle against unjust enrichment is embodied in Article 2244ย of the Civil Code, which provides that a person who acquires or comes into possession of something at the expense of another without just or legal ground must return it. To be applicable, Article 22 requires that: (a) a person is benefited without a valid basis or justification, and (b) such benefit is derived at another’s expense or damage.45
Inย University of the Philippines v. Philab Industries Inc., (G.R. No. 152411),46ย the Court’s discussion of the principle of unjust enrichment and the elements required for its application is instructive:
Unjust enrichment claims do not lie simply because one party benefits from the efforts or obligations of others, but insteadย it must be shown that a party was unjustly enriched in the sense that the term unjustly could mean illegally or unlawfully.
Moreover, to substantiate a claim for unjust enrichment, theย claimant must unequivocally prove that another party knowingly received something of value to which he wasย not entitledย and that the state of affairs are such that it would be unjust for the person to keep the benefit.ย x x x.
x x x x
In order thatย accion in rem versoย may prosper, the essential elements must be present: (1) that the defendant has been enriched, (2) that the plaintiff has suffered a loss,ย (3) that the enrichment of the defendant is without just or legal ground, and (4)ย that the plaintiff has no other action based on contract, quasi-contract, crime or quasi-delict.
Anย accion in rem versoย is considered merely an auxiliary action, available only when there is no other remedy on contract, quasi-contract, crime, and quasi-delict.ย If there is an obtainable action under any other institution of positive law, that action must be resorted to, and the principle ofย accion in rem versoย will not lie.47ย (Italics in the original, emphases supplied, and citations omitted.)
Thus, the principle of unjust enrichment does not automatically apply when one party benefits from the efforts or obligations of another. It is necessary to show that the enrichment of one party is without a just or legal ground, and that the plaintiff has no other action against the other party. In other words, there is no unjust enrichment when the person who benefited has a valid claim to such benefit.48ย Relevantly, the Court ruled inย Shinryo (Phil) Company, Inc. v. RRN,49ย that the principle of unjust enrichment is not applicable because the petitioner’s claim is based on contract,ย viz.:
As found by both the CIAC and affirmed by the CA,ย petitioner failed to prove that respondent’s free use of the manlift was without legal ground based on the provisions of their contract.ย Thus, the third requisite,ย i.e., that the enrichment of respondent is without just or legal ground, is missing. In addition,ย petitioner’s claim is based on contract,ย hence, the fourth requisite – that the plaintiff has no other action based on contract, quasi-contract, crime or quasi-delict – is also absent.ย Clearly, the principle of unjust enrichment is not applicable in this case.50ย (Emphases supplied.)
Also, the Court succinctly discussed inย National Transmission Corporation v. Misamis Oriental I Electric Cooperative, Inc., (Misamis Oriental)51ย that the contract between the parties prevails over the principle of unjust enrichment, thus:
The claim that Moresco I was unjustly enriched at the expense of petitioner is equally untenable for a simple reason. Because a contract exists between the parties,ย the obligations arising therefrom have theย force of law between the partiesย and must be complied with in good faith.52ย (Emphasis supplied and citation omitted.)
Here, NPC and BENECO executed a Contract of Sale of Electricity and a Transition Contract for the Supply of Electricity to govern their rights and obligations in the supply of electric power and energy. Therefore, any action that one may bring against the other shall be based on the provisions of their contract. The principle of unjust enrichment will not apply.
BENECO is liable for underbilled power
charges due to the use of a wrong
multiplier corrected within 90 days from
receipt of the erroneous billings.
Section 25 of the Transition Contract defines BENECO’s right to retain a portion of the underbilling and NPC’s right to correct billing errors and demand payment for underbilling.
ADJUSTMENT DUE TO INACCURATE METERS AND ERRONEOUS BILLINGS WITHIN A BILLING PERIOD.
25. In the event that aย billing is found erroneous due toย wrong reading, arithmetical mistakes orย omissions, SUPPLIER shall send CUSTOMER a debit/credit memo within ninety (90) days from the date of bill’s receipt to correct the error. SUPPLIER shall also be deemed to waive any claim on any billing error if it fails to send notice of such billing error to CUSTOMER within ninety (90) days from billing date.ย Provided that if the error is due to an inaccurate meter, said error may be corrected anytime.53ย (Emphasis supplied)
Inย Misamis Oriental,54ย the Transition Contract of the parties contained a similar provision on erroneous billings. In that case, the Court interpreted Section 25 and identified the two categories of errors in billing asย (1) error due toย a wrong reading, or an arithmetical mistake orย omission, which may be corrected only within ninety (90) days from the date of the customer’s receipt of the bill, else, the claim shall be deemed waived;ย and (2) error due to an inaccurate meter, which may be corrected any time. The Court upheld the Energy Regulatory Commission (ERC) and the CA’s findings that failure to use a metering device with the correct multiplier constitutes an omission under the First category,55ย thus:
The ERC decided in favor of respondent, and the CA affirmed the judgment.
We find no reversible error in the CA’s affirmance of the ERC ruling.
The ERC concluded that Transco failed to provide the correct meter multiplier when it installed the new meter – a clear omission that resulted in an erroneous billing.ย This finding was affirmed in the CA ruling which we quote in full and with approval:
We hold that the error in the billing due to an application of an incorrect meter is anย omissionย within the ambit of the first sentence of Section 25,ย Annex C to the TSC. x x x.
[x x x x]
The error committed by petitioner Transco was an omission because it Tailed to use the correct meter device, that is, one with a multiplier of 5,250,ย notwithstanding its admission in the Meter Test Report that it used the said multiplier. When Transco and Genco computed the billings for respondent MORESCO I for the months following the installation of the new meter device, they belatedly discovered that the new device had a multiplier of 3,500 instead of 5,250. This explained the under-biilings. We note that when Transco installed the new meter device, it believed that the multiplier of which was 5,250 when, in reality, it was 3,500. The error was caused by Transco’s own act of installing a meter device with a multiplier of 3,500 which was different from what it was supposed to install, that is, one with a multiplier of 5,250. Stated differently,ย Transco’s omission consists in failing to install a device with a 5,250 multiplier.ย If there was any error in the present case, it was only in Transco’s belief that the internal multiplier of the new meter device was 5,250 instead of 3,500.ย Considering that a multiplier is an inherent component of every meter device, as Transco expressly so stated, the correct meter device with a multiplier of 5,250 could have been available to it or, if not, within its means to obtain, had it only exercised ordinary diligence.56ย (Italic in the original, emphases supplied, and citations omitted.)
Similarly, in this case, the underbilling sought to be collected by NPC arose from NPC’s failure to set the CTR at 150/5, which resulted in the use of a wrong multiplier. This constitutes an omission under the first category of billing error of the Transition Contract.ย It was established during the trial that the determination of the correct billing multiplier is NPC’s sole responsibility.ย NPC even conducted several billing meter system tests before it energized BENECO’s Irisan Substation. Since then, NPC indicated 5,196.31 as the multiplier in BENECO’s monthly bills. NPC’s witness, Engineer Edgardo Orencia, confirmed that the meter was accurate, and what was erroneous is the multiplier used.57ย Additionally, remarks in Billing Meter Test Reports dated August 15, 2000, June 15, 2001, and July 30, 2003, indicate that the meter is accurate.
Thus, NPC can only correct erroneous billings arising from the use of a wrong multiplier within ninety (90) days from BENECO’s receipt of the erroneous billings. Here, BENECO received the letter informing it of its underbilling from May 2000 to February 2004 amounting to P157,743,314.43 onย May 17, 2004.58ย Billings received by BENECO beyond the 90-day period before May 17, 2004, can no longer be corrected, and NPC is deemed to have waived any claim on the billing errors beyond that period. BENECO is only liable for the underbilling on erroneous billings that BENECO received fromย February 17, 2004 to May 17, 2004.
Notably, NPC’s demand letter merely provides for the total amount of the underbilling covering May 2000 to February 2004, without reference to the amount of underbilling every month. With this, the Court cannot determine BENECO’s liability. It must be emphasized that mathematical computations are factual questions, and the Court is not a trier of facts.59
Hence, the case must be remanded to the RTC for proper determination of the amount of the underbilling.
Panay Electric, Ridjo Tape, and Meralco
do not apply.
Panay Electric,60ย Ridjo Tape,61ย andย Meralco62ย differ in some factual circumstances and applicable laws from the case at bar. Inย Panay Electricย andย Meralco, the contracts between the parties do not have specific provisions for billing errors. Inย Panay Electric, the Court applied the principle ofย estoppel in paisย in ruling that respondent Hotel del Rio is not liable for the deficiency billings because of Panay Electric’s use of a wrong multiplier factor. The Court held that Panay Electric is the only one to blame for such mistakes, repeatedly made, arising from culpable negligence of its employees.63ย Inย Meralco, the Court denied Meralco’s right to demand payment of the differential billing because it failed to provide a factual or legal basis for its claim. Withal, the Court emphasized that Meralco could have easily verified any possible error in the statements of account given its technical knowledge and experience in providing electric service.64ย Meanwhile, as in this case, the Court applied the Service Agreement between the parties inย Ridjo Tapeย in denying Meralco’s claim for the full amount of the differential billings. The Court explained that Meralco has the imperative duty to make a reasonable and proper inspection of its apparatus and equipment and the due diligence to discover and repair defects; failure to perform such duties constitutes negligence.65
If at all,ย Panay Electric, Ridjo Tape,ย andย Meralcoย cases are applicable to remind the obligation of the entities engaged in the supply or distribution of electricity to discharge its functions with utmost care and diligence. The Court’s discussion of the rationale behind the ruling inย Ridjo Tapeย is instructive:
The rationale behind this ruling is that public utilities should be put on notice,ย as a deterrent, that if they completely disregard their duty of keeping their electric meters in serviceable condition, they run the risk of forfeiting, by reason of their negligence, amounts originally dueย from their customers. Certainly,ย we cannot sanction a situation wherein the defects in the electric meter are allowed to continue indefinitely until suddenly the public utilities concerned demand payment for the unrecorded electricity utilizedย when, in the first place, they should have remedied the situation immediately. If we turn a blind eye on MERALCO’s omission,ย it may encourage negligence on the part of public utilities, to the detriment of the consuming public.66ย (Emphases supplied.)
By the same token, the Court cannot allow NPC to recover the underbilling in full in this case lest the consuming public will suffer. Whether an electricity supplier or distributor is a public utility or a government-owned and controlled corporation, it is expected to discharge its functions with utmost care and diligence. NPC cannot avoid its responsibility by imputing participatory negligence on BENECO. On this point, the CA elucidated:
NAPOCOR, in an effort to veer away from responsibility, desperately impute participatory negligence on the part of BENECO by accusing it of not doing anything to investigate its unusually low systems losses during the covered period x x x as it showed more electricity being sold by BENECO to its consumer than what it was paying. NAPOCOR argue that this, alone, was enough to arouse a suspicion on the part of BENECO on the CTR setting in its Irisan substation.
It should be mentioned, however, that the systems losses of BENECO as reflected on its Monthly Financial Statistical Report submitted to the ERC, covered its entire operation, not only the Irisan substation, thus, BENECO had no way of knowing the systems loss for each of its substations. Furthermore, We have noted the self-serving testimony of Engr. Banayat, defendants’ witness, expounded merely on the negative systems losses of BENECO, without giving any attention as to the instances when BENECO reached the average of twelve to eighteen percent (12-18%) systems loss mark set by the National Electrification Authority. Besides, as correctly argued by BENECO, there were only two (2) occasions when BENECO incurred negative systems losses.
And to be sure, even if these incidents were enough to arouse suspicion on the part of BENECO, it should be emphasized that the negative systems losses transpired in 2003 or three (3) years away from the time that CTR was set by NAPOCOR’s employees. And contrary to NAPOCOR’s posture of BENECO’s negligence, the records readily reveal that BENECO did make a move in 2004, or a year later. As gleaned from the records, it was BENECO’s employee, Engr. Umaming, who was to be credited for the discovery of the problem and with the consent of BENECO, lost no time in calling the attention of defendants thereafter.
In any case, even assuming for the nonce that BENECO was feigning ignorance about the low CTR setting, the inescapable conclusion at the end of the day is that defendants were still directly responsible for what happened due to their own negligence. For they could have, as they should have, increased the billing multiplier to the correct setting of 150/5. If, as defendants insist that BENECO cannot be said to be ignorant not to immediately determine something was amiss with the billing multiplier, then a lot more should be expected from them. It was incumbent upon NAPOCOR to protect its own business interest considering full and exclusive access to the billing meter and the pertinent data regularly gathered from such.
As it is, however, defendants did not do what they ought, to do. They never lifted a finger even as they had all the ways and means to detect the problem and to correct the billing multiplier at the soonest time possible. Instead, they casually went on with their business dealing with BENECO for four (4) years, as if nothing was amiss at the Irisan substation.67
At this point, we stress that NPC was unaware of the error in its billing system. Were it not for BENECO’s honest intention to raise and correct the possible irregularities in the NPC’s billing system, NPC would not have discovered the wrong CTR setting and multiplier. NPC’s attempt to pass the blame to BENECO for allegedly waiting for four years to report the matter to it is unjustified because NPC has the sole obligation to determine the correct CTR setting and maintain its billing meter system in the first place. BENECO does not even have access to NPC’s billing meter system. Regardless of who discovered the irregularities, it is undeniable that NPC failed to discharge its functions with utmost care and diligence. Therefore, it must bear the consequences of its own negligence.
BENECO is entitled to a prompt payment
discount.
The Policy Statement68ย provides that a customer is entitled to a 3% prompt payment discount on the total monthly bill due provided: (a) the total monthly bill is paid in full within the discount period, and (b) the customer has no unpaid account including any restructured account with NPC. Inย Misamis Oriental,69ย the Court maintained the ERC’s ruling that Moresco I is still entitled to a PPD since it is willing to pay a portion of the underbilling based on Section 25, but NPC and TRANSCO refused.70
The parties do not dispute that BENECO has been paying its current monthly bills promptly. Although BENECO did not offer to pay a portion of the underbilling, as inย Misamis Oriental,71ย it recognized its liability to pay the underbilling relating to the power bills corrected within the 90-day period in its Complaint.72ย Since BENECO’s unpaid underbilling is still undetermined and disputed when NPC revoked the PPD on June 23, 2004, BENECO cannot be considered to have any delinquent account. Hence, BENECO is still entitled to a PPD. NPC cannot unilaterally revoke the discount on the basis of BENECO’s supposed unpaid billings. We quote with approval the following disquisition of the CA:
Insofar as the discontinuance of BENECO’s prompt payment discount, as well as the disconnection of BENECO’s power supply, We are likewise convinced that [NPC] had no clear legal right to do so. It was premature on the part of [NPC] to withhold the application of the prompt payment discount and to disconnect BENECO’s power supply on the basis merely of its self-serving interpretation of their contract. The right of [NPC] to collect the same from BENECO, as well as the correlative obligation of BENECO to pay the amount supposedly due, was still highly disputable.
On this score, We agree with the court [a]ย quoย that for as long as BENECO was paying its current obligation to [NPC] on time, the latter was bound to honor its obligation to extend the discount, notwithstanding the existence of its deficiency assessment against BENECO. x x x.73
A final note. This is not the first time the NPC used a wrong multiplier, and this case will probably not be the last if the Court allows NPC to recover the underbilling at any time. The Court cannot foster a culture of inadvertence, complacency, and nonchalance in public service. It is unimaginable how NPC overlooked the wrong CTR setting for four years when its personnel conducts monthly readings to compute BENECO’s power bills. BENECO’s discovery of the possible irregularity, level of familiarity, and technical knowledge does not, in any way, reduce, negate, or even out NPC’s egregious mistake and gross negligence, which caused a significant loss on the part of the government, and ultimately of the people.
ACCORDINGLY,ย the petition isย PARTLY GRANTED.ย The Decision dated August 29, 2014 and Resolution dated May 22, 2015 of the Court of Appeals in CA-G.R. CV No. 96352 areย MODIFIEDย in that Benguet Electric Cooperative, Inc., is liable for the underbilling arising from the use of a wrong multiplier received from February 17, 2004 to May 17, 2004. Civil Case No. 04-CV-2055 isย REMANDEDย to the Regional Trial Court of La Trinidad, Benguet, Branch 63, to determine the amount of the underbilling in accordance with this Resolution. The Regional Trial Court isย DIRECTEDย to conduct the proceedings with reasonable dispatch.
SO ORDERED.
Perlas-Bernabe, (Chairperson), Lazaro-Javier, Rosario,ย andย J. Lopez,*ย JJ., concur.
_________________________________
Footnotes
*ย Designated additional member per Special Order No. 2822 dated April 7, 2021.
1ย Rollo, pp 17-37.
2ย Id. at 43-61. Penned by Associate Justice Rodil V. Zalameda (now a member of the Court), with the concurrence of Associate Justices Ramon M. Bato. Jr. and Maria Elisa Sempio Diy.
3ย Id. at 62-63.
4ย Id. at 180-187. Penned by Presiding Judge Benigno M. Galacgac.
5ย Id. at 188-191.
6ย Id. at 200.
7ย Id. at 25.
8ย Id.
9ย Id. at 201.
10ย Id.
11ย Id. at 203.
12ย Id. at 44.
13ย Id. at 44-46.
14ย Id. at 79-80.
15ย See id. at 83.
16ย See id. at 89.
17ย Id. at 181.
18ย Id. at 67-78.
19ย Id.
20ย Id. at 70-72.
21ย Id. at 95-96.
22ย Id. at 182.
23ย Id. at 180-187.
24ย 256 Phil. 260 (1989).
25ย 350 Phil. 184 (1998).
26ย Rollo, pp. 182-186.
27ย Id. at 186.
28ย id. at 186-187.
29ย Id. at 188-191.
30ย Id. at 50-51.
31ย Id. at 52-53.
32ย Id. at 60.
33ย Id. at 62-63.
34ย Id. at 25-27.
35ย Supraย note 24.
36ย Supraย note 25.
37ย 637 Phil. 80 (2010).
38ย Rollo, pp. 27-29.
39ย Id. at 31-33.
40ย Supraย note 24.
41ย Supraย note 25.
42ย Supraย note 37.
43ย Reyes v. Lim, 456 Phil. 1, 14 (2003).
44ย ART. 22. Every person who[,] through an act of performance by another, or any other means, acquires or comes into possession of something at the expense of the latter without just or legal ground, shall return the same to him.
45ย Car Cool Phis., Inc. v. Ushio Realty & Devt. Corp., 515 Phil. 376, 384 (2006), citing 1 J. VITUG,ย CIVIL LAWย 30 (2003).
46ย 482 Phil. 693 (2004).
47ย Id. at 709-711.
48ย Supraย note 45, at 384.
49ย 648 Phil. 342 (2010).
50ย Id. at 352.
51ย 793 Phil. 704 (2016).
52ย Id. at 714.
53ย Rollo, p. 90.
54ย Supraย note 51.
55ย Supraย at 707
56ย Supra at 712-713.
57ย Seeย Rollo, p. 189.
ATTY. GAYO:
Q x x x in this particular case, the meter was accurate?
A Yes Sir.
Q What was inaccurate was the multiplier used?
A Yes Sir, that’s right.
x x x x
58ย See id. at 79.
59ย Seeย Hanjin Heavy Industries and Construction Co., Ltd. v. Dynamic Planners and Construction Corp., 576 Phil. 502, 520 (2008).
60ย Supraย note 24.
61ย Supraย note 25.
62ย Supraย note 37.
63ย Supraย note 60, at 270.
64ย Supraย note 62, at 110.
65ย Supraย note 61, at 194.
66ย Supra, at 195.
67ย Rollo, pp. 53-54.
68ย A. Full Three Percent (3%) Discount
(a) Customer shall be entitled to a 3% prompt payment discount on the total monthly bill due provided that the total monthly bill is paid in full within the discount period, and provided further that customer has no unpaid account including any restructured account with NPC.
69ย Supraย note 51.
70ย Supra, at 709.
71ย Supra, at 69.
72ย Rollo, p. 71.
73ย Id. at 58.
Batas Pinas


